HomeNewsNational Grid energises first Hinkley Point T-pylons running through Somerset

National Grid energises first Hinkley Point T-pylons running through Somerset

-

National Grid has this week successfully energised 36 of the world’s first T-pylons between Bridgwater and Loxton in Somerset, including some which run past the villages of East Huntspill and Mark.

The new T-shaped pylons have been constructed as part of the £900 million Hinkley Connection Project, a new 57 km high-voltage electricity line that will connect six million homes and businesses to new sources of home grown, low carbon energy and help the UK to meet its net zero by 2050 target.

High-voltage electricity – up to 400,000 volts – is now passing through the T-pylons, a newly constructed electricity substation at Sandford and 8.5km of underground cables through the Mendip Hills Area of Outstanding Natural Beauty. A further 80 T-pylons will be completed and energised by 2024.  There will be a total of 116 T-pylons along the whole 35mile route.

Construction of the first T-pylons began in September 2021, with all the conductors or wires that transmit the energy between Bridgwater and Loxton installed by March 2022. The conductors are now energised and transporting electricity around the National Grid’s electricity network.

The T-pylon design, the first major UK redesign since 1927, has a single pole and cross shaped arms, and is around a third shorter than traditional high-voltage pylon design with a smaller ground footprint.

The new design was selected from over 250 designs entered into an international competition run in 2011, organised by the Royal Institute of British Architects and government (the then Department of Energy and Climate Change).

With a need for new energy infrastructure to enable progress towards net zero, the competition sought a new design to reduce impact on the local environment and surroundings.

Along with offshore routes, underground cabling and continued use of traditional lattice pylons, the new T-pylon design is a potential technology choice for future projects. Each new transmission network project is assessed on a case-by-case basis, with the technology used by National Grid based on planning policy and regulations set by Ofgem as well as engineering, environmental and cost considerations.

Steven Haskayne, Project Director for National Grid, says: “We’re extremely proud to have reached this significant milestone on the Hinkley Connection Project.”

“The T-pylons are now reinforcing and strengthening the network in the South West and are ready for the connection of low carbon energy when Hinkley Point C starts generating.”

“This new design forms part of our significant investment in the network in England and Wales, adding capacity onto the grid to deliver low carbon electricity to millions of people across the UK to use for years to come, and helping the UK’s journey towards net zero.”

The T structure is the first amendment to the traditional lattice design in nearly 100 years. The lattice pylon was the winning entry in a 1927 pylon design competition ran by the Central Electricity Generating Board, chosen by architect Sir Reginald Blomfield.

In March 2022, wires to carry low carbon energy onto the UK electricity network were installed on 36 of the Hinkley Connection Project’s new T-pylons in a process known as ‘stringing’, as Burnham-On-Sea.com reported here.

First pylon is toppled in Burnham area to make way for new T-pylons

Oops! National Grid starts investigation after crane gets stuck building new T-pylons

 

TODAY'S MOST VIEWED NEWS

WEATHER

Burnham-on-Sea
overcast clouds
12 ° C
13.3 °
11.3 °
96 %
0.9kmh
100 %
Wed
15 °
Thu
14 °
Fri
14 °
Sat
14 °
Sun
13 °